Lobby Renovation January 2025

Please make sure your management company/renters are aware
of the lobby renovation.  It will be noisy at times.

Mail and packages will be available for pickup.
After 5:00pm will cut down on the traffic in the renovation area.

1/6/2025 The Lobby Renovation Has Started, An Exciting Day. This Photo Shows All The         Different Items In The Ceiling.  There Is Electrical, Plumbing & HVAC.

 

1/6/2025 Preparing The Ceiling For Temporary Plastic Wall Going Up.

 

1/6/2025

 

1/6/2025 There Will Be A Walkway From The Sliding Driveway Door To The First Floor.                    As The  Email Stated From The Board, The Doors Going To The Embassy Will  Be Locked           During  Renovation. The Embassy Locked Their Doors And We Posted Signs.

 

1/6/2025 Grid Work Coming Down Tomorrow

 

1/6/2025

 

1/6/2025 The Electrician, HVAC and Glass Company Coming Tomorrow

 

1/6/2025 Temporary Wall With Caution Signs

 

1/6/2025 End Of Day 1

 

1/7/2025 Day 2, Measuring Space To See If We Can Cut Off Some Of That Big Wall & Looks                          Like We Can

 

1/7/2025 Photo Taken From Owner’s Room Of The Wall That Used To Have Brick On It.  The                 Electrician Is Rewiring What Is Needed  For Temporary Lights So They Can Remove                         The Rest Of The Grid Work

 

1/7/2025 Stone Wall With a Mural On Side

 

1/7/2025 Almost All Sides Are Down On The Partial Wall That Used To Have The 1980s               Mural.  Tom  Met With The HVAC Guys, Electrician and Waiting On The Glass Company                    To Remove The Glass  In The Owner’s Lounge.

 

1/7/2025 End of Day 2. Ceiling Grid & Lobby Glass Will Come Down Tomorrow

 

1/8/2025 Start Of Day 3. Removing The Sheet Rock On The Wall Going To The Embassy

 

1/8/2025  Most of The Grid Work Is Down and Temporary Lights Have  Been                             Installed.

 

1/8/2025 This Is The Long Wall By The Embassy Walkway

 

1/8/2025 The Stone & Mural Walls Are Done. Some Of The Studs Will Be Removed To Make           That Wall Smaller.

 

1/8/2025 Wall By Embassy. Two Sheet Rocks, Back to Back, Serves As a Firewall

 

1/8/2025 Stone Wall Side

 

1/8/2025 This Photo Has The Stone Wall On The Right

 

1/8/2025 Cleaned Up For The Day With The Middle Wall Down

 

1/8/2025 Standing By The Stone Wall Looking Towards The Driveway

 

1/8/2025 Long Wall Going To The Embassy. End Of Day 3

 

1/9/2025  Day 4, Lounge Cleaned Out and Ready For Tile Removal

 

1/9/2025 Removing Tile

 

1/9/2025 Standing In FOAK’s Office Looking Into Where The Vending Machines Were. Slop            Sink On The Right. All The Walls Are Coming Down and Their Office and Will Be Open To The       Electrical and Washer/Dryer Areas.  The Hallway Leading Into Their Office Will Be Closed Up          and Used for The New Mailbox Area.  The Hallway Leading Into the Mailboxes Now Will Be     FOAK’s  New Entrance

 

1/9/2025 Slop Sink Would Be On The Left. The Washer Will Be Moved and a Dryer Added.                    A New Utility Tub Will Replace The Slop Sink.  FOAK Uses The Washer and Dryer For All               Their Mop Heads, Towels etc.  They Will Be Happy To Get A Dryer.

 

1/9/2025 FOAK’s Office Looking Into The Vending Area

 

1/9/2025 End of Day 4, Tile Chipped Out In Homeowners Lounge

 

1/10/2025 Mid Day 5, Photo Is Taken From Where The Vending Machines Used To Be

 

1/10/2025 Inside FOAK’s Office Taken From Doorway

 

1/10/2025 Photo Taken From The Door Entering The 1st Floor

 

1/10/2025 Photo Taken From The Driveway Sliding Doors

 

1/10/2025 Tile Almost Done Throughout

 

1/10/2025 Hallway Standing At The 1st Floor Door

 

1/10/2025 Photo Taken From Standing By Door Going To The Embassy

 

1/10/2025 Standing By Door Going To The Embassy

 

1/10/2025 End Of Day 5.  They are Working Tomorrow To Keep On Schedule

 

1/11/2025 Start of Day 5, Photo Taken From Door Going To 1st Floor

 

1/11/2025 This Is FOAK’s Office. Most Owners Haven’t Seen This Area. It Was 3 Separate              Rooms With Their Office, Electrical Room and Cleaning Area. This Will All Be 1 Large Area.               The Wall On The Left Is The Restroom

 

1/11/2025 Photo Taken From Maintenance Office Door

 

1/11/2025 Photo From The Embassy Door

 

1/11/2025 Photo Taken From 1st Floor Door Looking Towards The Driveway.

 

1/11/2025 Tile and Thin-Set Being Removed From In Front Of The Elevators.

 

1/11/2025 This is The Area Entering FOAK’s Office

 

1/11/2025 Entrance Into The Mail Room

 

1/11/2025

 

1/11/2025 FOAK’s Office Area

 

1/11/2025 Photo Taken From The Door Going To The Embassy

 

1/11/2025 Standing By The Owner’s Lounge. End of Day and Will Start Back Up On Monday.        Only a Small Amount Of Tile Left In FOAK’s Office Area. 99% Of The Ceiling Is Done. Now              That It’s All Open The Electrician, Plumber and HVAC People Can Evaluate Everything.  The        Front Elevators Were Shut Down For A Short Period Of Time.  Our Building Is Pretty Empty So              It Was a Great Week To Start The Reno

 

1/13/2025 Start Of Day 7. Lobby Glass Coming Down

 

1/13/2024 Owner’s Lounge Is Gone

 

1/13/2025 Bathroom Getting Cleaned Out

 

1/13/2025 Looking Into FOAK’s Office

 

1/14/2025 Photo Taken From Where The Homeowner’s Lounge Was

 

1/14/2025 Driveway Sliding Door On The Left. A Portion Of The Wall Was removed That Will      Open Up That Area. The Old Part Is In Dark Areas

 

1/14/2025 Old Stone Wall, End Of Day

1/14/2025
Lobby Renovation Video 1

Lobby Renovation Video 2

Lobby Renovation Video 3

1/15/2025 Mail Boxes Being Moved. All Packages and Mail Will Be Available For Pick Up Just            In A Different Location. They May Be Moved A Few Times During The Construction.  If             Owners  Can Get Their Mail/Packages After 5:00pm It Will Help With The Traffic

 

1/16/2025 Mailboxes Moved

 

1/16/2025 Mailbox Temporary Location

 

1/16/2025 End Of The Day.  Demo is Done on Schedule, No Surprises.  A Couple Minor Things         Left That Will Be Taken Care of at the Right Time, Like The HVAC In This Photo.                    Electrician   Rewired In FOAK’s Back Office, Slop Sink Area &  Electrical Room.  The HVAC,   Plumbing and Electrical Are All Being Addressed  Work Will Resume Next Week.  The Floors         Will  Be Ground    Down To Make For a Smooth Surface.  Framing Will Begin So That Will                 Be Exciting

 

1/10/2025 These Will Be The Signs Going Throughout The South Hampton. This One Is In                 The Garage Lobby

 

New South Hampton Signs With Our Logo. These Are What Our New Signs Will Look  Like.           Once We  Move Through The Building, All The Signs Will Match.

 

1/6/2025 Areas Patched Where Old Signs Were

 

1/6/2025 The Painting Begins.  Painting Will Continue When It Warms Up

 

1/6/2025 Landscaping Going On Around Our Building

 

1/8/2025 Landscaping Continues

 

1/8/2025 Still Removing Rocks

 

1/11/2025 Landscaping Done So Far Up To The Garage Entrance.


January 2025 Cart Corral in Garage

2024 Renovations